Hello All,

I want to ask you about automatically created Planned Independent Requirement. I have a material number (A).

When I do "execute forecast" in MM02 for material A, the forecast values are created.

Then I run MRP from MD02 for material A.

When I looked at MD04, I saw the planned independent requirement quantites are the same as forecast values. How could it be? Can the system automatically created PIRs by reference material forecast?

For doing this, which field is need to fill in MM02?

Thank you for your support...