Hi Experts,

Here I am facing very unique problem. in Fund management BCS (New).

Earlier we were using CoCd 1020. Management has taken decision to change CoCd from 1020 to 1090. Therefore I copied 1020 and created new Cocd 1090.

I have also assigned fund management area 1020 (which were assigned to Cocd 1020 and was working fine).

Client is only using Payment Budget.

I can create budget through FMBBC, same budget can be released through FMMPRELE. after posting entries consumed budget is not getting updated in system, i.e. we can not see consumed budget amount in FMRP_RW_BUDCON...

Regards,

Yogesh Kshatriya.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi, do you have derivation for posting addresses? I mean if you posting to CI 1-1-1 in document appear CI 1-1.

Also check if this posting is not statistic

yogesh_kshatriya2
Active Participant
0 Kudos

Thanks for concern...

But just 10 min before issue has been resolved. The budget update check at company code level was missing...