on 12-28-2011 4:23 AM
Hi Experts,
I have assigned a group to human activity. And my requirement is whoever in the group can access the task at any time. Task is generated for that group & all the user assigned to that group is able to see the task.
Issue is when one user click the task(status is changed from New to Inprogress) the task is claimed by that user & hence the rest of the user couldn`t see the task in their worklist. So i want to have that task to be accessed by any users in that group at any time. Please help me on this.
Regards,
Arun.
Hi Arun,
This is the expected behavior from SAP BPM. Once you assign the task to yourself you should complete it or re-assign it to someone else.
If anyone in the group completes the task the task is said to be completed. Otherwise you can assign some boundary conditions like time limit (if the task is not completed on time) and move the task to administrator.
Thanks,
Soujanya
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Arun,
A single task can be claimed by only one user. If you want to send a single task to multiple users then you need to apply the concept of looping. Refer this blog [Parallel (multi-instance) Activities in BPM CE 7.2|http://www.sdn.sap.com/irj/scn/weblogs?blog=/pub/wlg/20229] [original link is broken] [original link is broken];
Regards
Arjun
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
84 | |
23 | |
11 | |
9 | |
8 | |
5 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.