Plan driven procurement scenarios difference

Hello Guys

Could you please tell me the major differences between

plan driven procurement standalone,

plan driven plant maintenance and

plant maintenance supplier integration.

I want to know the major difference between these three scenarios.

Highly appreciated if you provide some short type notes on your understanding rather than detailed SAP links.

Thanks, looking for your reply.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Dec 27, 2011 at 04:46 PM

    Hi Santhosh,

    Plan driven plant maintenance refers to the scenario where MRP run generates your PR and this is PR is sent to SRM as a shopping cart in sourcing cockpit from where the purchaser can create bid invitation or assign a supplier to create a PO.

    Plant maintenance supplier integration refers to the MM-SUS scenario where PO created in MM is sent to supplier who confirms the order, sends a PO response/ASN/Invoice.

    Regards,

    Nikhil

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.