on 12-27-2011 1:14 PM
hi,
I want to know how to pull the next inspection date field in UD screen
hb
hi,
u need to extraxt the field in UD screen, for that u need to use user exit.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Enter "inspection interval" time in QM view of material master. So system will update Next inspection date = GR date + inspection interval time
Guess GR date = 01.Jan.2012
Inspection interval in QM view - Material master = 31 days
System will update next inspection date = 01.Feb.2012
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
But the scenario comes mostly for the reccuring inspection. If the material is batch managed you can activate the 09 inspection type in the material master inspection set up and the inspection interval for the material. For the reccuring inspection you can trigger the lot using QA07 or you can plan it in the back ground.