Project Definition Dates Change Log

Hi PS Gurus,

Please let me know if there is any way to find out the Project Definition/WBSE change dates log in any report.

I could not find in CN60 and CJCD.

Also tried to find the same in CDHDR/CDPOS but could not find the change log for dates.

Thanks

Vikas

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Dec 27, 2011 at 08:33 AM

    Did you activate "Change Documents" in the project profile? CN60 will display data only if the change documents is activated.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Dec 27, 2011 at 09:49 AM

    Yes, The change Document is ticked in configuration, but Project Start/End date change log is not reflecting anywhere..

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Dec 27, 2011 at 01:12 PM

    Hi,

    Sometime it may possible for some field SAP does not have given change Log. Still needs to re-look in details and find if it is there or not. For status its you can get change log in different table like JCDS. And for other field normally change log get saved into CDHDR and CDPOS table as you mentioned correctly.

    If it is not there for your required field then it will be worth checking requrement and its necessity then if required check with ABAPer. whether it will be possible for him/her to get and save in some Z table or update standrad tabel with some Change Object Number. May be possible as we did in one of our Z development. ou may need to create Change Object and then change key number. Something like that ...I dont remember exactlly the naming convention/field names.