Hi CTM Experts,
We are plannng to use CTM and for which i am setting up a simple model in system.
Model is for 1 DC and 1 Plant. 1 SKU which is extended in both the location. PPM exist in Plant.
Have done the followin thing:-
1) Master Data Selection
2) Time stream for 90 days
3) Using demand priotization by MBDAT - Material Availability Date and WMENG- Requested quantity. While pressing Simulation button in the tab, seeing demand are correctly selected.
4) Supply categorization - using CC,AI,AJ,AK,AL.. There no available supply in system in terms of stock and planned order. If i press simulation in the Tab , it confirms the same. CTM search strategy is Seq1-CC, Seq2-***** Source Determination *****.
5)Using Plannin Mode:Replan all orders, Scheduling direction:backward, Pegging-Fixed, Delete Mode:Do not delete any order,
With all this basic setting , if i execute CTM run , it finished with Green status, but no demand is fulfilled. And it says "4 demand not fulfilled".
Questions: What i am missing?? Any config? Any masters which i feel not the case.
Any suggestions welcome.