Subcontracting info record

is it mandatory to have a info record in sap for subcontracting scenerio

suppose if i do not create a info record then what is going to happen

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Dec 23, 2011 at 09:47 AM

    Hi,

    It is not mandatory to have a Sub-contracting Info record. U can do sub-contracting cylce without Info record.

    Regards,

    Chowdary

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 23, 2011 at 09:52 AM

    HI,

    Plz read note - 858239

    It can contain information about the Product Version, and thereby serve as source to determine the BOM to be used in a SC Purchasing document.

    It can contain Price conditions, which are adopted into any SC purchasing document (with Item Category = L) as document conditions.

    However, it is important to realize some differences in behaviour:

    The Subcontracting Info record is created for the header material only. NOT for the components.

    Only for the header material it makes sense to relate to a Production Version because this is what determines the alternative BOM and hereby the components in it

    The Subcontracting Info Record must be Plant-specific, in order to be able to relate to the production Version. (The Version field is not visible otherwise!)

    When the Subcontracting info record has price conditions then the net price deriving from the conditions is dealing with the labor done by the subcontractor.

    It will not be used to update the Material Average Price on the Material Master

    The cost price will be found later as the labor + the cost of the components included.

    For a Purchase requisition it is not possible to determine the correct Product Version, even the Vendor is specified. It will just pick the first valid version it can find.

    When creating the Purchase Order from this Requisition, you will get a pop-up which allows you to let the "correct" production version overwrite the one coming from the Requisition. This is the case, when you create a PO with a vendor that has a different production version assigned in its info record as it is included in the Requisition.

    Thanks,

    Yogesh

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.