Skip to Content
avatar image
Former Member

Document XXXXXXXXXX is not completely processed; recognition not yet possib

While running RR I am getting this error Document XXXXXXXXXX is not completely processed; recognition not yet possible.

Diagnosis

Processing of the sales document is not yet completed. It

is possible that there will be a change to the revenue

recognition data after the sales document is saved.

Therefore, revenue recognition cannot currently take place

at this time for this document.

System Response

There is still an entry in table VBREVC.

Procedure

Save the sales document again so that any changes are

included in the revenue recognition data. This can also

take place using the report intended for this purpose

SDRRAV54 (update of SD documents). Revenue recognition is

possible again after this.

I went to VF42 and it doesn't show anything with the billing document in the work list. We use RR type D. Any suggestions how to correct this?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Dec 22, 2011 at 05:29 AM

    Dear Pankaj,

    Please check your sales order, It is still incomplete.

    Go VA02 --> Edit --> In completion Log.

    Regards,

    Sandip

    Add comment
    10|10000 characters needed characters exceeded