Skip to Content
avatar image
Former Member

How to capture dates of attaining status REL, CNF for all steps in project?

Hi All

I'm making a report where i need to capture dates of REL & CNF status of every step in a project. After entering project number/WBS element in table AFVC I'm getting object number [OBJNR]. But when same is entered in JCDS syatem says data doesn't exist. I'm able to view the same OBJNR in JEST where I get whether status is active or inactive.

I'm getting OBJNR for main project from PRPS & able to get dates of main WBS from JCDS.

My entire development is stucked due to this.

Please help.

Regards

Nachiket

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Dec 20, 2011 at 12:43 PM

    Hi,

    I think I can contribute something here:

    First of all you need Object Number for each PS Operative Objects and you can get those from following tables:

    Project Def: PROJ

    WBS Element: PRPS

    Network: AUFK

    Activity: AFVC

    Then I beleive you have to pass this OBJNR into table JCDS. Here you have filter out/remove STAT lines having INACT as X.

    Also if some STAT line get repeated then consider highest Change Number line and accordingly make your I_TAB.

    Now you have some STAT line with UDATE and UTIME. Now you can get these STAT description by passing these STAT into table TJ02Twith Language value as EN. Here you will get Status Description as well.

    Please try one and let me know whether it will work or not.

    Thank you.

    Swapnil Kharul

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      This might be helpful,

      Tick the following in Project profile-control-Basic data-Document change

      Open project in cj20n.

      Goto EDIT-Status-System/users status

      Extra - Change document - all

      we can get the history of change status.