No work item starts after the post of a leave request

Hi experts,

I use the workflow 12300111 to deal my leave request in ESS. For the ESS, I use the standard iview which is based on webDynpro for java and is provided by EHP4.

I parametered the table T554S_WEB to define the workflow 12300111 which should be used for each subtype in IT2001.

I also checked in transaction SWU3 to make sure that the automatic workflow customizing is maintained.

But my problem is, no work item starts when I post a leave request from the portal. In transaction SWIA, nothing has been detected after I posted my request.

An other problem, the name of manager appeared in the iview of portal who will approve the leave request is not correct. In stead, it's the employee's name which appeared in the portal.

Could anyone help me to resolve these two problems ?

Thanks a lot,

Wuyia

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Dec 20, 2011 at 04:16 PM

    Please can you check whether other workflows are getting triggered. Please check from SWI2_FREQ. If yes then there is some problem with your configuration. Please try to do so again and if there is customizing task do a SCC1 in the test system.

    Thanks

    Arghadip

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Thanks Arghadip,

      I saw there are a lot of task TS12300097 and TS12300116 getting triggered one year ago in SWI2_FREQ, but they are all in german. Now we need the workflow for the webdynpro java whose jco connection is in french. Does it make the problem ?

      And I don't understand your second sentence :

      Please try to do so again and if there is customizing task do a SCC1 in the test system.

      Thanks

      Wuyia

  • Dec 20, 2011 at 11:58 AM

    Hi,

    But my problem is, no work item starts when I post a leave request from the portal.
     In transaction SWIA, nothing has been detected after I posted my request.

    Make sure that the workflow template is made as general task(agent Assignment)

    And talking about the manager name i hope in the rule groups settings may be the option LINE manager is choosen, so if you choose this option and enable the option user to enter the manager name then it picks the line manager based on the ORg Structure.

    So you need to check for spro settings with respect to the rule group.

    Regards

    Pavan

    Add comment
    10|10000 characters needed characters exceeded

    • Hi,

      Chekc the BADI PT_GEN_REQ is active or not, because in this BADi implmenetation class there is a method called start workflow this method is responsible to start the workflow. Try to insert a break point and chect what is the happening in this method.

      Regards

      Pavan

  • avatar image
    Former Member
    Dec 21, 2011 at 10:23 AM

    Hi,

    Thanks for all your help. The problem is resolved. Actually the characteristic PLOGI is not actived for the new WERKS..

    Best regards,

    Wuyia