Dear Gurus,
We need a heuristic which should do the following:
a. Finite backwards scheduling
b. Take setup time into consideration (setup matrix)
c. Order priority
The closest heuristic I got was Schedule Sequence (SAP001) with algorithm /SAPAPO/HEUR_PLAN_SEQUENCE. However this performs a current date scheduling.
Does SAP have any other heuristic which meets the above mentioned criteria? I have searched a lot but couldn't get one.
Thanks in advance!
Snigdho