Schedule FPY1 payment run automatically on daily basis in background

Hi All,

As I couldn't find the answer using search, then created new topic.

I have requirement to schedule multiple FPY1 Payment Run jobs in background so that we also can execute the printout of cheques and payment lists. The requirement is that jobs are run daily at 8AM for different business partners, the printouts are sent to spool and values date and posting date in FPY1 variants are updated automatically.

Tried to do it via RFKK_MA_SCHEDULER transaction as per this instruction: http://help.sap.com/saphelp_crm700_ehp01/helpdata/en/69/acf816ccc8426c8d6408a54b6517fa/content.htm

but not successfully as job is executed only once.

How can we ensure that due date and payment date is copied over - do we use some events?

How can we then execute printout of cheques and payment lists - do we use SM36 to schedule report SAPFKPY3 as another step after FPY1?

Currently the OSS notes available doesn't answer these questions.

Thanks a lot for your time and help!

Kind Regards,

Martins

<div id="isChromeWebToolbarDiv" style="display:none"></div>

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Best Answer
    avatar image
    Former Member
    Feb 22, 2012 at 12:46 PM

    Hello.

    I have just finished implementing this functionality.

    Use programme RFKK_MA_SCHEDULER and create variant with activity type PAYP, after creating a "template" in FPY1 (I used a template in FPY1 with ID_Date "31.12.9999" and ID "AUTOM". This template can have the settings you want to use for your daily runs (company code settings, bank settings, etc...) and should be saved but not scheduled.

    In my requirement I needed to implement a logic that calculates the due date, posting date, the reconciliation key, and the name of a user list to be used in the field "Business Partner - Preselection"). I used the event 1741 to implement the calculations I needed for my parameters, that are replaced in the FPY1 template I mentioned earlier.

    The only thing I need to do is schedule the execution of the programe RFKK_MA_SCHEDULER with the activity PAYP, and set the execution frequency required. Et voilà.

    Jean-Marie

    Add comment
    10|10000 characters needed characters exceeded

  • Feb 23, 2012 at 06:12 AM

    Hi,

    Have you looked at using transaction FKJOXTR? It's a powerful tool for scheduling and running mass activities.

    It might be overkill for your simple requirement, but it allows you to set up chains of mass activities, define dependencies, run SM37 jobs in-between, and so on.

    You use events 1901 - 1906 to help control the runs.

    It's a bit hard to get your head around it at first, but it does a wonderful job once it is set up.

    cheers

    Paul Bakker

    Add comment
    10|10000 characters needed characters exceeded

  • Dec 20, 2011 at 04:01 PM

    Martins:

    Also look at RFKK_MASS_ACT_PARAMETER where you can copy parameters into new runs.

    regards,

    bill.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Dec 21, 2011 at 06:06 AM

    Hi Martins,

    Try this:

    1. Create your own custom report and schedule this report with different variants:

    2. In this report do below steps:

    2.1 Create a dummy identification in FPY1 to act as source for other runs and read them using 'FKK_AKTIV2_PARA_BASICS_FROM_DB'

    2.2 Create a new Date Id and identification and check if they already exists using 'FKK_AKTIV2_PARA_BASICS_FROM_DB. Do this step in a DO loop so that if it already exists you can proceed ahead with other

    2.3 Now copy the new parameter using 'FKK_PARAMETER_COPY'.

    2.4 Build the mass key using 'FKK_AKTIV2_RUN_KEY_CONSTRUCT'.

    2.5 Schedule the mass run using 'FKK_AKTIV2_RUN_START'.

    Thanks.

    Ravi