hi all,
we are using PS + PP.
we creating bom against wbs element
MRP run on wbs element and process continues.
here i need to ask one question.
we have four sections in PS :
DESIGN, PROCUREMENT, PRODUCTION & DISPATCH.
BOM CREATED ON PRODUCTION WBS ELEMENT AND MRP RUN ON SAME WBS ELEMENT SO MY PROCUREMENT IS DON ON PRODUCTION WBS ELEMENT AND I COULDN'T GET CLEAR REPORT.
IS THERE ANY WAY THAT I WILL CREATE BOM ON PROCUREMENT WBS ELEMENT. PR / PO GETS CREATE AFTER MRP RUN ON PROCUREMENT BUT CONSUMPTION OF RAW MATERIALS WILL BE DONE AGAINST PRODUCTION ORDERS WHICH HAVING ASSIGNMENT OF PRODUCTION WBS ELEMENT. BUT IT SHOULD DONE BY AUTOMATIC PROCESS NO MANUAL PROCESS INVOLVE.
THANKS IN ADVANCE.
Edited by: SIng on Dec 20, 2011 2:32 AM