on 12-19-2011 10:36 AM
Dear.
In trx. ME2O I can consider requirements from subcontracting purchase order and purchase requisition.
Do you know a solution in order to consider also requirements from subcontracting planned orders ?
Thanks.
hi,
yes you can consider that production orders also included in this report.
Thanking you
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
closed without solution.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I see only flag to consider requirements from SC purchase requisitiion.
Where can i consider requirements from SC planned order ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.