on 12-16-2011 12:46 PM
Hello,
We are facing an issue in the CJ20N
Project- WBS- Network Order- Activity- Materials are attached to it
For ex- Material number 23 is added to the network as per the business process the Purchase requistion will automatically get created.
Now we are facing an issue.
When we add the same material to the activity, the purchase requistion is not created auotmatically, we are not able to view the purchasing data tab.
The moment we add this material, it's stating reservation for network.
Previously it was showing up as purchase requistion for network.
Please help us in knowing what could be the possible reason for this behaviour.
Regards,
prashanth
Hi,
Probably the activity was released in first case and not in second. Please check parameter 'Res./Purc. req.' on 'Proc. Param' tab of material component, the value here controls when PR will be generated. Hope that helps.
Regards
Shrikant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
check the item category for the material that you are assigning to the activity.if n system should automatically creates pr for network. if l system generates the reservation automatically.
regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vengaiah,
MRP View is maintained for the material where the PR needs to be created.
Regards
Prashanth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
If stock exists in your storage location. then systems create the reservation. Please check your inventory. Then run MRP all reservations will be converted to Pr's if there is no stock.(assuming that material item category L). IF you want directly to create a PR then take the stock as Item category N.
Thanking you
Vengaiah Chowdary
Hi
Check your material master data for ICG, Procurment type and ICI indicators. If some thing was set wrongly, then correct those errors in master data. Delete the material which was sitting on network and re-enter sytem automatically creates Preq.
As per your thread, ICG in mater data might have set for NORM and ICI indicator must 2.
@Vengaiah: Item category N or L, system cteates Preq that depends on how you set up your material master data.
If IC=N, then it must be designated as a dropship item and not as a stock item and you master data must be ICG/Procurment type/Indicative collector indicator - BANS/F/1!
Regards,
PSR
Edited by: PSR on Dec 16, 2011 4:29 PM
Hello,
Thank you for all the answers,
I would need additional info from your end to moveahead with theprocess.
One thing we have observed is when we select a material and try to add it again, the procurement will automatically getting picked up as WE. and we can see the reservation in General data tab.
One more observation initially under the procurement parameters, under the value flow and /quantity flow.
intially it was showing up as 1, now it's showing up as Q
Please let me know where are these configuration done, since i am very new to PS module.
Regards,
Prashanth
Hi,
I guess so. "WE" is causing problems for you. WE stands for Reservation Plant stock. Do one thing. Do not maintain any procurement indicator in the network profile in transaction OPUU. When you attach a material to the activity in CJ20N system will pop up a window. Here you can choose the way in which the material needs to be handled.
Try this out and revert.
Regards,
Gokul
Hi,
Please check if mrp views are activiated for the material.
Thanking you
Vengaiah Chowdary
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.