No Actual Cost in CNS40 Report

Former Member
0 Kudos

Dear All,

I am not able to get actual cost (of PO) in the Report CNS40.

Please Suggest

Regards

Prashant

Accepted Solutions (1)

Accepted Solutions (1)

sunil_yadav2
Active Contributor
0 Kudos

Hi Prashant,

Cost of PO is not an Actual Cost, where as this will be considered as commitment cost. this PO cost will be shown in CJI5.

thanks

Sunil

Former Member
0 Kudos

I have done grn and Miro for the for the same still the actual cost is not reflected

Prashant

sunil_yadav2
Active Contributor
0 Kudos

Hi Prashant,

Please check this cost in CJI3.

check Account Assignment Category in PR & PO.

thanks

Sunil

Former Member
0 Kudos

Hi,

There is no cost in CJI3 report

The account assignment catagory in PR & PO is Q-Proj. make-to-order.

Please Suggest.

Regards

Prashant

sunil_yadav2
Active Contributor
0 Kudos

hi,

can you please tell us about your business scenario.

thanks

Sunil

Former Member
0 Kudos

Please award points....

Former Member
0 Kudos

Provide solution first .........

PP

sunil_yadav2
Active Contributor
0 Kudos

Hi Prashant,

Can you please check Report CNS41 instead of CNS40. this report will give you detailed costing.

else you can tell process which you are following

Thanks

Sunil