In this scenario after creation of PO it is possible to change the PO, but Our client requirement is not to change PO after creation .how this is possible ,is there any special configuration for that ?

Thanking You;

Regards;

Joydeep Mukherjee

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Dec 15, 2011 at 03:54 AM

    Hi,

    For this kind of restriction you config the Release strategy for you PO in such a way that make the changability option and cannot be changed in below path.

    Materials Management-Purchasing-Purchase Order-Release Procedure for Purchase Orders-Define Release Procedure for Purchase Orders-Release indicator-make changability as option 1 which is cannot be changed.

    This way you can restrict you PO from further changes.

    Thanks

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 15, 2011 at 04:05 AM

    HI,

    There are two possible solution for you

    1) Don't allow authorization of t-code ME22N to user ,if you don't want change in PO,so no one can change it,this can be achieve with help of BASIS consultant

    2) You can apply release strategy configuration in such way that once PO create no one can change it

    for more info on release strategy check following link

    [http://sapmmhelp.blogspot.com/2008/11/release-procedure-release-strategy-main.html]

    Regards

    Kailas Ugale

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 15, 2011 at 04:07 AM

    hi,

    in standard their is no that facility for normal p.o but you can restrict that at enduser level don't give that authorization to that enduser for this you have to consult your basis person.

    other wise you have to restrict through relese startgy for p.o

    for configration of relese startgy go through this link

    http://www.saptechnical.com/Tutorials/Workflow/POReleaseStrategy/page1.htm

    http://www.sap-basis-abap.com/sapmo017.htm

    Thanking you.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.