To Set the ProductionOrder status as TECO

Hi Gurus,

I am new to PP Module. Can you please guide me how can i set a released Production order status as TECO.

Thanks

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on Dec 14, 2011 at 06:25 PM

    Hi,

    Go to T. Code CO02. Enter order number. Enter. Click functions--restrict processing--complete technically. This way you can set TECO status.

    Also you can revoke the TECOed order into REL status.

    Hope it helps you.

    Regards,

    Alok Tiwari

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 14, 2011 at 07:57 PM

    Hi there,

    you could also set this as a mass change with using COHV.

    If You want to set the TECO automatically when the deliered qty equals to the order qty set the COHV with using relative dates and define a background job running at night time. this is a normal mass processing in many cases.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.