Is there a way to escalate actual values in planning from a previous year by a % into the current year's budget values?

Is loading budget values via catt script the only way you can load them other than manually. Is there a canned sap program you can use that would allow you to load tens of thousands of records?

Thanks,

Jon "Sap Newbie"

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • Posted on Dec 14, 2011 at 09:27 PM

    Hi Jon,

    The answer is Yes.

    Try KPU1 tcode that creates a "Revaluation

    Additional aids are:

    -KSPU - Revaluate costs

    -KP97- Copy Plan to Plan

    -KP98- Copy Actual to Plan

    I hope it helps,

    Regards,

    Dave

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 15, 2011 at 03:00 AM

    For KP26

    Enter all related parameters and select F5

    Go to MENU-Edit-Change Values

    Enter either revaluation factor % or value

    You can check for other transactions as well

    Srinivas

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.