SUBCONTRACTING PO

hI gurus,

Is it possible to create subcontracting po without BOM ? Please suggest how to achieve it

Thanks & regards

sangita

Add a comment
10|10000 characters needed characters exceeded

Related questions

5 Answers

  • Best Answer
    Posted on Dec 15, 2011 at 03:53 AM

    HI,

    IF don't have BOM then you have to give material component manual in PO,But without giving component it is not possible,

    BOM is not mandatory but component is mandatory

    IF you have BOM your time will save to give component in PO

    for more info check following link

    [BOM in Subcontracting ??;

    Regards

    Kailas Ugale

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 14, 2011 at 05:37 PM

    I dont think it is possible.

    Please check the link below.

    [Link between subcontracting p.o and BOM;

    Regards

    Sayan

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 14, 2011 at 05:49 PM

    Hi

    Sayan is right. It's not possible. Please, see SAP Note 205454 - Documentation on subcontracting and see also the attached document, it's so usuful. Take into account that SC is a process of procuring materials to your subcontractor that need certain components that you must delivery. These components are in your BOM or in alternative BOM.

    I hope this helps you

    Regards

    Eduardo

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 14, 2011 at 06:21 PM

    Hi,

    As explained by experts above it is not possible leave component field blank while using item category L in PO but we would like to know what is the business requirement. Can you please let us know your business scenario which requires creation of subcon PO (w/o component) and can not be achieved via normal PO?

    Thanks,

    Yogesh

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 14, 2011 at 06:40 PM

    Hi,

    The subcontracting items (SC items) in purchasing documents are represented with a special item category L. This means that for each SC item, one or several sub-items have to be entered for the components to be provided. If there is a bill of material (BOM) with the components for the material to be procured, then the components are copied from this BOM into the subcontract item. You can also enter the component(s) manually or add the components from the BOM. There is no config required!

    A Subcontracting purchase order is the price of the vendor subcontracting work and the materials provided by the subcontractor. You can define conditions for subcontracting in a subcontracting purchasing info record.

    You can also provide components without reference to an SC order by entering another transfer posting with movement type 541 and manually entering the requested materials, quantities, and subcontractor.

    Hope this helps!

    Reetesh

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.