Hi
I have REM MTO scenario.
I have created Scheduling agreement for Finished product and material availability date is 30.12.2011.
Iam using prodction version,, Inhouse production time is 1 day, schd. margin key is 000, no Gr processing time.
After running MRP, planned order is getting start date as 21-12-11 and end date 22-12-11. Iam doing lead time scheduling.
There are no holidays on factory calendor,
Please inform why date is 21.12.11.