Dec 14, 2011 at 11:54 AM

Dates in planeed orders

36 Views

Hi

I have REM MTO scenario.

I have created Scheduling agreement for Finished product and material availability date is 30.12.2011.

Iam using prodction version,, Inhouse production time is 1 day, schd. margin key is 000, no Gr processing time.

After running MRP, planned order is getting start date as 21-12-11 and end date 22-12-11. Iam doing lead time scheduling.

There are no holidays on factory calendor,

Please inform why date is 21.12.11.