Hi

I have REM MTO scenario.

I have created Scheduling agreement for Finished product and material availability date is 30.12.2011.

Iam using prodction version,, Inhouse production time is 1 day, schd. margin key is 000, no Gr processing time.

After running MRP, planned order is getting start date as 21-12-11 and end date 22-12-11. Iam doing lead time scheduling.

There are no holidays on factory calendor,

Please inform why date is 21.12.11.

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Dec 14, 2011 at 12:21 PM

    I hope you mean that u have date in plan order as 21.12.2011. If yes then please note that for lead time scheduling it absilutely necessary that standard value in routing and standard formula in work center is correct and control key in routing has schedule selected.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 14, 2011 at 12:34 PM

    Dear

    Please check the planning table MF50 what exact Scheduling u have maintained Prod./basic dates

    then check the availability you have maintained

    Also Check OPKP

    With Regards

    Pushpalas

    Edited by: pushpalas on Dec 14, 2011 1:35 PM

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.