How to in Update process of SP's with Upgrade of Add on

Hi,

I'm updating the system to the latest ECC 6.0 STACK 20.

This includes various SP's and also, in my case, a update of PI_BASIS (version 2005 to 2006).

My question is, should I update the PI_BASIS in SAINT to the SP0 of 2006 version, and then continue the update of the other components (HR, BASIS, FI, EA-HR, ...) on the SPAM and also the update of the 2006 version to the latest SP?

Or is there another way?

Thanks

Pedro

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Dec 14, 2011 at 11:15 AM

    Hi,

    You should updated the components based on the dependency. Check dependency of PI_Basis component from transaction SPAM and based on the dependency upgrade those component first and then update PI_Basis.

    Thanks

    Sunny

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Pedro Taveira

      Hi,

      Please check dependency of PI_Basis 2006 SP i.e. what is component version required for other component in order to upgrade PI_Basis to 2006. If you meet that dependency then you can follow either approach.

      Thanks