md01 mrp run restriction to planned independent requirement- any exits or logic available

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi Ganapathy,

We have user exit in SAP for to make this possible but only if you can explain us your exact scenario.

1. Does your plant have Pure MTS material only or it has Both MTS and MTO.

2. We can use User exit in SAP to restrict the Material number selection based on MRP controller but it will be usefull if your scenario is PURE MTS (10).

3. If you have other strategy such as 40,50 etc where both PIR and MTo is considered for planning then we have look into other option. So please explain your scenario in detail.

Former Member
0 Kudos

make to order

saled order mrp run we will create- planned order using md50

through mdo1- i want to restrict demand should come from only planned independent requirement- through md61

madlercm
Active Contributor
0 Kudos

Please try to explain your requirement from a business process perpective, because it is not clear and it also doesn't make any sense as it is phrased.

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

You should consider BAdI MD_CHANGE_MRP_DATA.

The following statement is available on BAdI documentation:

"You can use the Business Add-In (BAdI) MD_CHANGE_MRP_DATA to change the MRP data that is read during the following processes.

- Planning run of material requirements planning, master production scheduling, and long-term planning

- Creation of the stock / requirements list

- Planning table of repetitive manufacturing

Using the available BAdI methods, you can implement a user-defined logic when importing the MRP element from the database.

In the processes mentioned above, the internal table MDPSX is built up from the MRP elements read from the database. In the standard logic for MRP, it is defined whether an MRP element is taken into account in the MRP and in which form (for example quantity, date).

You can use this Business Add-In to

- Take into account MRP elements in certain cases, although they are never taken in to account according to the standard logic.

- Not take into account MRP elements, which are considered according to the standard logic.

- Change characteristics such as MRP relevance, dates, quantities and so on, of imported MRP elements

You can define in your implementation whether you want to take action in the display only or also in planning."

BR

Caetano

former_member184655
Active Contributor
0 Kudos

Dear Ganapthy,

What's your exact requirement during MRP run through MD01?

M61X0001 can be used for selecting the materials based on MRP type,MRP controller.

Come back with your exact requirements.

Regards

Mangalraj.S

Former Member
0 Kudos

REQ- MD01- MRP RUN- SHOULD CONSIDER DEMAND CREATED IN MD61- ONLY

NOT ANY OTHER REQUIREMENTS ,

Former Member
0 Kudos

Hi,

yes try this logic.

make all pir in inactive version from md62.

Thanks and regards