Is there any standard transaction or BAPI/BADI to assign multiple materials viz 1000 plus to an Inspection plan.

Thanks

Anup

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Dec 14, 2011 at 12:33 AM

    You have two option to upload mass materials to inspection plan.

    Option1: Go to QP02 --> Material assignment screen. Here you can assign 14 materials at a time and do page down to assign next 14 materials. This is time consuming activity.

    Option2: With help of techinical person develop LSMW/ BADI which call QP02 to update material assignment in inspection plan.

    Please find few relavent descussion below, I hope it will help you take decisioon.

    [mass-assigning-of-inspection-plans]

    [mass-assign-material-to-inspection-plan]

    [mass-material-assignment-in-inspection-plan]

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.