on 12-13-2011 10:59 AM
Hi Gurus,
When I am activating "Confirmation control key 0004" in the existing Scheduling Agreements(created with reference to contracts) system is giving the error "Confirmation control key 0004 not allowed" .
So kindly let me know will system accepts the confirmation if the schedules already partially delivered?
Regards,
A.S.K
Hi,
You cannot change the confirmation control key if partial delivery exists for that SA
Refer this Link
http://www.sap-img.com/materials/explain-about-the-po-confirmation-control-key-in-detail.htm
Edited by: redriver on Dec 13, 2011 12:34 PM