Confirmation Control Key 0004

Former Member
0 Kudos

Hi Gurus,

When I am activating "Confirmation control key 0004" in the existing Scheduling Agreements(created with reference to contracts) system is giving the error "Confirmation control key 0004 not allowed" .

So kindly let me know will system accepts the confirmation if the schedules already partially delivered?

Regards,

A.S.K

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

You cannot change the confirmation control key if partial delivery exists for that SA

Refer this Link

http://www.sap-img.com/materials/explain-about-the-po-confirmation-control-key-in-detail.htm

Edited by: redriver on Dec 13, 2011 12:34 PM

Former Member
0 Kudos

HI,

Thanks for yor beautiful reply that means if i want to activate ASN with the existing Scheduling agreements system will not allow.

Am i right? If that is the case how to operate?

Regards,

A.S.K

Former Member
0 Kudos

Dear Sridhar,

I am afraid you can't change it for the existing SA

Because confirmation control key is a important control parameter related to shipping notification

Another work around is close the existing SA (Delivery completed indicator)

Create new one with desired confirmation control key

Former Member
0 Kudos

Thanks driver you drived it nicely.

I am happy with your solution.

Regards,

A.S.K