We are facing issues with usage of PPDS PDS 5.0 in APO.
We have ciffed the PPDS PDS with Material components and operations. These are visible in PDS as components and modes The recipe of the FG is such that the material assignments are done phase wise. On running a PPDS heuristics on a sample FG material code, the Order generated doesnu2019t show
- In Operations in the Context view,
- Considers no time from the PDS and
- Doesnu2019t show any dependant demands on the raw materials created either.
All FG and RM Materials, related resources are in active integration models.
If however, we remove the material assignments as phase wise from the Recipe, recif and rerun the PPDS heuristics, now the material requirements get created. However, the operations and hence capacity data is still not considered during creation of an order.
Request inputs urgently.
Thanks,
Sudhir