    Hi,

    The integration point of PP and CO is in

    Work center: Where we mention cost center and activity types

    Routing: where activity types values are maintained

    Production order: where we do cost analysis in GOTO-COST-Analysis.

    Hope it will help you.

    Regards,

    Alok Tiwari

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      HI ,

      You can check with following CO point with PP:-

      1. You need to define cost structure like primary & secondary element of costing.

      2.Create cost Center & Activity type and assing it to work center.

      3.Then you may need to run price planning KP26.

      4.When you doing this config setting then after at the time of order creation check Goto->Cost -> Order Balance.

      5.Order settlement using co88 or k088 if any variance need to calculate varinace using KKS1

      Hope this helpful for you if any issue revert back.

      Regards,

      Prd_87

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.