What are the costing settings for pp point of view
Hi,
The integration point of PP and CO is in
Work center: Where we mention cost center and activity types
Routing: where activity types values are maintained
Production order: where we do cost analysis in GOTO-COST-Analysis.
Hope it will help you.
Regards,
Alok Tiwari
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI ,
You can check with following CO point with PP:-
1. You need to define cost structure like primary & secondary element of costing.
2.Create cost Center & Activity type and assing it to work center.
3.Then you may need to run price planning KP26.
4.When you doing this config setting then after at the time of order creation check Goto->Cost -> Order Balance.
5.Order settlement using co88 or k088 if any variance need to calculate varinace using KKS1
Hope this helpful for you if any issue revert back.
Regards,
Prd_87