Regarding Production planing datasources

Hi Experts,

I am new to pp environment, i have to extract data for Time of goods issued to production & time of production completed where can i get these fields, which datasource can match & which tables can give these fields can any one help for this probleam

Thanks & Regards

TP

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Dec 13, 2011 at 06:45 AM

    Hi,

    I think you are talking about SFG-FG TAT report which actually gived you Turn around time of a material at different stages like GI GR UD for SFG and then same for FG as well.

    I believe 2LIS_03_BF Datasource will help you in building this report.Based on different movement types you need to calculate GI GR UD date and time.

    Lot of understading and logical work need to be done for this report.Ask your functional consultant to help you out in building the logics and understanding the calculation at different stages.

    Some logic needs to be written in routines to transform the data based on the requirement and some at query level.

    This is little complex report so please be clear in requirement gathering and analyze fit gap analysis pretty well.

    Hope it helps.

    REgards,

    AL

    Add a comment
    10|10000 characters needed characters exceeded

    • Hi,

      As i already explained you above that 2LIS_03_BF Datasource will give you the needed information.

      Whatever i know functional regarding it i will mention it.

      GI DATE----POSTING DATE restricted with movement type 261
      
      GI TIME----Posting Time restricted with movement type 261
      
      GR DATE---POSTING DATE restricted with movement type 101
      
      GR TIME---Posting Time restricted with movement type 101
      
      DISPATCH DATE--POSTING DATE restricted with movement type 601
      
      DISPATCH TIME--Posting Time restricted with movement type 601

      Posting date and Posting time is avaialable in the above mentioned datasource.

      Please get in touch with your PP consultant as i said earlier also that lot of anaysis and understanding needs to be done for the same.

      Regards,

      AL

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.