I have run into a business process that I cannot find a good solution in SAP for, it's regarding the following flow:

1. We have a return receipt on a material A (this is an assembled item that consists of e.g. B, C & D)

2. After return it turns out that component D has not been returned

3. The stock needs to be adjusted in order to reflect this (Remove article A from stock and add B & C to stock)

4. The preferred solution direction would be similar to the 309 movement type (which does not work)

5. Our customer wants a very easy solution (because the work volume is quite high)

I'd appreciate your input on solving this issue,

Thanks, Mark

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Posted on Dec 12, 2011 at 07:00 PM

    Hi Mark,

    Based on your scenario I am assuming that you have BOM maintained for material A with components as B, C and D in CS01 tcode. If yes, then as per standard return process you must be creating a return PO and postings against that will put compentns B , C and D back in inventory. now as we do not have component D physically in warehouse but our return PO above posted that in inventory so we would be doing reversal transaction to remove stock of component D from system.

    This is what i understood but would like to know why you wanted to peform a material to material transfer?

    Thanks,

    Yogesh

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 13, 2011 at 04:15 AM

    HI

    First thing you want return stock to whom and from where means you want return to vendor or else?

    second you are saying 309 not working can you explain which problem you are getting for same?

    309 is material to material transfer and prerequisite for same is

    1) Both material should have same base unit of measure ( material D and can say material X)

    2) you can transfer from unrestricted stock to unrestricted stock only in this 309 movement type

    Regards

    Kailas Ugale

    Edited by: kailasugale on Dec 13, 2011 9:45 AM

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 13, 2011 at 05:56 AM

    Hi,

    Is this subcontracting scenario.. where u issue B,C,D to job worker to assemble A.

    Job worker has used only B,C and D is unused and remain with job worker..

    If thats the case during receipt of material u can untick the component D during GRN BOM explosion..

    So that stock remains with job worker. Now u can issue this A material along with Material D to job worker to get back A material.

    The faults of this method are:

    1. During stock check the actual usable material is not actually present in stock until u issue it back to job worker to attach material D

    2. The stock value need to be analyzed since material A is issued back to jobworker. If u are using batch valuated material then it would be ok..

    Please check whether it is applicable.

    sBk

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.