Hi all,

Sometimes we send expensive spare parts to other companies in case of emergency, and get them back when they have it in a few days.

When a material is sent to a vendor with 541 movement (Transfer posting unrestricted-use stock - stock of material provided

to vendor ), the MRP for that material should not create planned orders for that material. Because it is thousands of euros expensive and it will be back in stock in a few days.

After automatic MRP run, planned orders are checked in MD15 and these ones are removed from list for not to create purchasing requests for them.

What can be done to prevent MRP create planned orders for materials that a posted with 541 movement?

Thanks in advance,

Koray

Edited by: ktulumen on Dec 12, 2011 4:51 PM

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Dec 13, 2011 at 07:58 AM

    Thanks for the reply.

    In OVZ9 I have a table like this:

    Av. Check - Descrp. - A. Check Rule - Checking rule

    01 Daily requirements 01 Checking rule 01

    01 Daily requirements 03 Checking rule 03

    01 Daily requirements A SD order

    01 Daily requirements AE SD order; make-to-order stock

    01 Daily requirements AQ SD order; project stock

    01 Daily requirements AV SD order; returnable packaging

    01 Daily requirements AW SD order; consignment

    01 Daily requirements B SD delivery

    01 Daily requirements BE SD delivery; make-to-order stock

    01 Daily requirements BQ SD delivery; project stock

    01 Daily requirements BV SD delivery; returnable packaging

    01 Daily requirements BW SD delivery; consignment

    01 Daily requirements PM Checking rule for plant maintenance

    01 Daily requirements PP PP checking rule

    01 Daily requirements PS PS Checking rule (project system)

    01 Daily requirements RP Replenishment

    01 Daily requirements RS Checking rule (SAP Retail Store)

    01 Daily requirements SM Service checking rule

    02 Individ.requirements 01 Checking rule 01

    02 Individ.requirements 03 Checking rule 03

    02 Individ.requirements A SD order

    02 Individ.requirements AE SD order; make-to-order stock

    02 Individ.requirements AQ SD order; project stock

    02 Individ.requirements AV SD order; returnable packaging

    02 Individ.requirements AW SD order; consignment

    02 Individ.requirements B SD delivery

    02 Individ.requirements BE SD delivery; make-to-order stock

    ......

    What line should I enter to enable stock at subcontarctor available?

    "Availability check" value for those materials are "02".

    Thanks.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 12, 2011 at 04:14 PM

    MRP run does not exclude certain materials, except you define a logic in a user exit.

    It creates a new planned order if it determines a requirement for that material for which you do not have a coverage.

    As a material never falls from heaven, you should create a regular process.

    which means either you have to change your cusotmizing in OVZ9 to make stock at a subcontractor available

    or you need to create a PO to that other company to get the material back and to include this PO into your planning process.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 13, 2011 at 08:54 AM

    OK, When I select ATP Quantities, the error text is:

    Diagnosis

    In Customizing the checking control for the combination availability 02 and checking rule BO was not maintained.

    System Response

    This material component cannot take part in the availability check.

    Procedure

    Maintain the relevant entries in Customizing or ask your system administrator to do this for you.

    Procedure for System Administration

    Maintain the relevant entries in Customizing for the availability check.

    Any idea where to edit?

    The easy way is to create an order for that company, but customizing is less prone to user error.

    Edited by: ktulumen on Dec 13, 2011 9:58 AM

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 13, 2011 at 09:04 AM

    OK, never mind. 😊

    Thank you very much.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.