Hi,
For internal activities I am maintaining in SPRO, Time Porportionality and Work in Plan & Actual Methods as default values.
But even though it is showing the same in the Progress tab in the internal activity, the system is not calculating when you run Cne1.
Only when I am selecting Time Porportionality & Work methods, individualy for all the activities in the Progress tab, the system is doing the calculation in Cne1.
If I maintain the methods as default in SPRO, I think the sytem should do the calculation even if I do not select individualy for every activities.
2. Another point is, is there any way thru which I can maintain POC weight as 1 by default or any transaction for mass application?
Regards,
Abhra.