Dear Gurus,
I created sp.proc key in planning plant.I have done each and every setting req for this sp.proc key in planning and prod plant.But wen i run mrp in planning plant,so in my prod plant its only create pur req not the planned order.I want MRP should create both i.e planned order as well purch req in prod plant.Kindly suggest any settings for this.
Regards.