on 12-12-2011 6:26 AM
Hi all,
Can anyone tell where is the settings given for the special stock indicator E in Req type KE...
Regards,
Joseph.
Dear Joseph,
I guess this material must be planned using the planning strategy 20,for which after taking a MRP run,the system proposes a
planned order of order type KD and account assignment category as with E.
check the configuration settings for the account assignment category in T.code OPPS for the planning strategy 20.
and for this planning strategy planned materials the system creates planned order for the order type KD - individual customer
order.
Check and revert back.
Regards
Mangalraj.S