For one specific WBS element, user able to generate commitments beyond the budget tolerance despite having AVAC status active.

Please suggest if any thing needed to be done to prevent/correct this.

Thanks and warm regards

ramSiva

Accepted Solutions (0)

Answers (2)

Answers (2)

gerry_hodgins
Active Participant
0 Kudos

there is a lot of information in notes

574187 - 1424698 - 1160675

also noet 1160675 - maybe this offers

a hint as to why the budget was available

Ger

Former Member
0 Kudos

Hi,

Please check the settings in SPRO, Project System > Cost > Budget > Define Tolerance Limits for the related budget profile and set the availability Control action 3.

Hope this will help you.