Shutdown Planning of PM through PS

Former Member
0 Kudos

HI

Kindly suggest me how to planing the shutdown of PM module through PS module. is there any configuration required for this.

Thanks inadvance.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

create revision and include in shut down order and also include WBS in equipment master for settlement and same would be populated in additional tab of maintenance order.

Regards,

Sudhakar

Former Member
0 Kudos

hi

my query is what exactly the benefits when we assign the wbselement to the equipment and how to plan from the ps module.and how we can see the attached pm orders in wbs element in cj20n t.code.

Edited by: Subrahmanyam on Dec 12, 2011 9:43 AM

former_member388328
Active Contributor
0 Kudos

Hi,

There is some configuration which needs to be done. We need to create subnetwork with pm order type and assign the pm order to that subnetwork in your project.

Thanking you

Vengaiah Chowdary

Former Member
0 Kudos

hi chowdary,

what is the configuration required and how to proceed to create and assign the subnetwork. provide step by step guide. thanks in advance.

former_member388328
Active Contributor
0 Kudos

Hi,

It is not feasible to explain the configuration steps here.

Thanking you

Vengaiah Chowdary

Former Member
0 Kudos

Hi,

Path: SPRO > SAP Reference IMG > Project System > Structures > Operative Structures > Network > Define Parameters for Sub Network (OPTP)

Also use Transaction code ADPMPS to link PM and PS object.

Hope this will surely help you to proceed further. Isnt it?

Swapnil Kharul

Former Member
0 Kudos

Also ensure to check setting for Control Key in PS node.

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

Hi,

See - I just told you only main config steps which are required for Turnaround Project.

There may be other as well depending upon business needs...

For example like All cost should booked into Maintenance then we may need to use WBS Element as Statistical and same thing needs to be configured into Project Profile by selecting Statistical Check Box.

For one/two WBSE (Capex WBSE) we can remove this statistical check box by de-selecting manually.

Main steps are:

1. Project System-StructuresOperative Structures-Work Breakdown Structure (WBS)--Create Project Profile

2. Project System-StructuresOperative Structures-Network-Settings for Networks--Maintain network types

3. Project System-StructuresOperative StructuresNetwork-Settings for Networks---Specify Parameters for Network Type

4. Project System-StructuresOperative Structures-Network-Settings for Networks-Maintain network profiles

5. Project System-StructuresOperative Structures-Network---Define Parameters for Subnetworks

6. Project System-Costs-Object Class Default Values---Specify Default for Project Definition Object Class

7. Project System-Costs-Object Class Default Values---Specify Default for Network Header Object Class

8. Project System-Costs-Automatic and Periodic AllocationsSettlement-Specify Default Settlement Profile for Project Definition

9. Project System-Costs-Automatic and Periodic AllocationsSettlementDefine Settlement Rule for Network-Specify Default Settlement Profiles for Networks

10. Project System-Dates-Scheduling---Specify Parameters for Network Scheduling

11. Project System-Resources-Maintain Control Parameters for the Availability Check

12. Project System-Material-Availability Check--Define Checking Control

13. Project System-Confirmation-Define Confirmation Parameters

14. "Define Task List Usage Keys (0-Standard Network in Task List Usage 004)

It is required to Use PM work Center in Network screen"

15. "Factory calendar in project differs from plant factory calendar

needs to be changed to W8"

16. Project System > Structure > Operative structure > Network > Define Parameters for Sub Network

17. Control Key