Skip to Content

Total replenishment lead time (CIF)

Dear All,

Total replenishment lead time in Material Master in MRP3 not transferred to APO for Plant (Distribution Center )

All the data can be changed and transferred to apo without any issue

I note something in Total replenishment lead time but for Plant ( production planning ) can also be moved to APO

the problem only coming for this field for DC only

Please Advise

thanks & regards

Rami

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Dec 12, 2011 at 08:10 AM

    Hi Rami,

    Please first check into the help SAP link below:

    http://help.sap.com/saphelp_scm50/helpdata/en/d6/e7783739e6ff5de10000009b38f8cf/frameset.htm

    For in-house production, the field Total Replenishment Lead time should be transfered to APO, in field Checking Horizon, on master data tab ATP in APO. In cases of external procurements it will not work.

    Claire

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.