Dear All,

Total replenishment lead time in Material Master in MRP3 not transferred to APO for Plant (Distribution Center )

All the data can be changed and transferred to apo without any issue

I note something in Total replenishment lead time but for Plant ( production planning ) can also be moved to APO

the problem only coming for this field for DC only

Please Advise

thanks & regards

Rami

Accepted Solutions (1)

Accepted Solutions (1)

claire_yang
Contributor
0 Kudos

Hi Rami,

Please first check into the help SAP link below:

http://help.sap.com/saphelp_scm50/helpdata/en/d6/e7783739e6ff5de10000009b38f8cf/frameset.htm

For in-house production, the field Total Replenishment Lead time should be transfered to APO, in field Checking Horizon, on master data tab ATP in APO. In cases of external procurements it will not work.