Hi Experts,

I want to delete a BPM task from uwl. Am using NW CE 7.2 SP04.

My scenario as follows. I have two human tasks, Requester & Approver. Requester will submit the request with request id to the approver. Approver can send back the request to requester for more information.

Once Approver click the button "Return to Requester" then task will be genrated in both requester UWL & approver UWL & the status will be pending requester. When approver click on the pending requester task he can see two "Send Reminder" & "Closed No-Reply". When approver click "Closed No-Reply" if requester takes too long to reply then task will be completed from his UWL. But task in the requester will be still there.

So i when Approver clicks closed no-reply then the task in the requester also should be deleted/completed/hide.

Thanks,

Arun.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Dec 10, 2011 at 02:53 PM

    So you want to close the process when Approver chooses "Closed No-Reply", why dont you simply call Terminate Event when Approver clicks "Closed No-Reply" ..this will end the process.

    -Abhijeet

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.