Hi all,

If multiple PDS exist for a material, during MATP is there any fixed logic on which the PDS selection takes place.

Regards,

RS

Accepted Solutions (1)

Accepted Solutions (1)

michael_thinschmidt
Contributor
0 Kudos

Hi RS,

The system will take the PDS with the highest priority per default. If there is a shortage on the components the system will NOT switch to the next PDS to check this. Sorry, this is a missing functionality and I do not see a way to overcome this easily.

best regards,

Michael