on 12-10-2011 4:50 AM
Hi all,
If multiple PDS exist for a material, during MATP is there any fixed logic on which the PDS selection takes place.
Regards,
RS
Hi RS,
The system will take the PDS with the highest priority per default. If there is a shortage on the components the system will NOT switch to the next PDS to check this. Sorry, this is a missing functionality and I do not see a way to overcome this easily.
best regards,
Michael