Hello
I'm an auditor in a multinational company that uses SAP. I have came upon a case in which the overal budget for a WBS is 100,000 and the total value of the POs opened against this WBS is around 140,000. Invoices recorded against these POs are less than 100,000. I have checked in the WBS and saw that the budget control for it is activated.
I'm trying to understand what happened but I can't as of now.
Can someone help me?
Thanks a lot in advance