Former Member
Dec 09, 2011 at 10:37 AM

Multiple Counter Plans

21 Views

Hi

Can anyone help? I am trying to create a Multiple Counter Plan based on a cycle set of 250 hours or 5 weeks with a task list based on 250 hours that will give me a different service type at different intervals, for example at 250 hours operation 10 would be a B service, at 500 hours operation 20 would be a C service and so on. This task list works fine for a strategy plan but when used for a multiple counter plan all the operations are planned at the same time. I know I should be able to produce different types of visit and think the problem is in the cycle set but I've hit a brick wall.

Your help will be greatly appreciated

Paul