Hi Gurus,

The business have different testings that require some time to get the results. They need to sell the products even before the results are out. So they need to UD the ilot even if the tests are not yet done. How can we record the results if the ilot is already done with UD and the product is already sold?

Thanks for the help.

Eva

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Dec 09, 2011 at 07:42 AM

    Its not recommanded to do the Result recording after material is sold but still you can try to use the concept of "Long term Inspection "

    While creating a MIC ,check a control indicator ,tick on "Long term Inspection "

    This will allow you to do result recording after UD

    In a long-term inspection:

    There can already be a usage decision for the inspected material during the long-term inspection

    You can still record inspection results for long-term characteristics, once you have made the usage decision

    The system sets a separate status in the inspection lot to identify the long-term inspection and it provides special worklists and workflow tasks for this purpose

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.