on 12-09-2011 7:06 AM
Hi Guru's,
I have create a Contract with Sold to party, Ship to party and material combination. So when i am creating a Sales order for the same combination system is not proposing the availability of contract. I manually need to assign the contract to the sales order.
Am i missing any configuration. Can any one suggest the solution for the same.
It would be of great help.
Thanks in advance.
With Best Regards,
M. Rajendran.
Hi Rajendran M,
Maintain the copy control in VTAA
select your Sales document type & contract document type
In Header
Data T- 051
Data T- 101
Data T- 001
copying req- 001
check mark copy item number
in Item - select yourcontract item category
Data T- 151
Data T- 102
Data T- 002
FPLA- 251
copying req- 301
check mark copy schedules
x update document flow
pos/neg qty - +
pricing type- G
Let me know if your problem is solved
Regards
Pradeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.