I have created two PR an also i have released that PR. but in which t code i can see the budget for the particular PR.

Like what amount is consumed against the PR>

We are using the former Budgeting (4.7)

Regards

Sachin

Edited by: SAHOO_CIN on Dec 9, 2011 6:46 AM

Accepted Solutions (0)

Answers (1)

Answers (1)

iklovski
Active Contributor
0 Kudos

Hi,

Budget is not entered for particular document, but to the FM (budget) address which is a combination of two or more FM objects, e.g. fund centre, commitment item, etc. The budgetary assignment could be seen on PR in the 'account assignment' tab for the relevant line. The PR is consuming the budget of the address mentioned there (if it at all defined to consume the budget, because it's customizable).

Regards,

Eli

Former Member
0 Kudos

Yes, I know the concpt.

It depned's on fund centre & commitment item.

If i will go to the tcode: FMRP_RW_BUDCON - fund centre- commitment

the data is not flowing.

Regards

sSachin

iklovski
Active Contributor
0 Kudos

Hi,

FMRP_RW_BUDCON is a transaction for FM-BCS and you said that you are using former. Go to the reports of former budget, e.g. FMRP_3FMB4001or create your own report.