Hello!

We have some customer where we only can deliver at one day per week but the customers are sending schedules for every day of a week.

e.g.:

Customer A:

Delivery at Thursday for all schedules off the following week (Monday to Friday)

Customer B:

Delivery at Wednesday for Schedules from next Thursday to Wednesday

How can we set this in our system to get the correct planning by MRP?

Regards

Markus

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Caetano Almeida
Dec 21, 2016 at 06:49 PM
0

Hi Markus

You can use a planning calendar a lot sizing procedure PK to determine that MRP will generate planned orders in specific days of the week. However, this is a material master setting and it is not customer specific.

As a workaround, you can try to define a different storage location MRP area for each customer and a different planning calendar for each MRP area.


Regards,

Caetano