Skip to Content

special delivery date, planning by MRP run

Hello!

We have some customer where we only can deliver at one day per week but the customers are sending schedules for every day of a week.

e.g.:

Customer A:

Delivery at Thursday for all schedules off the following week (Monday to Friday)

Customer B:

Delivery at Wednesday for Schedules from next Thursday to Wednesday

How can we set this in our system to get the correct planning by MRP?

Regards

Markus

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Dec 21, 2016 at 06:49 PM

    Hi Markus

    You can use a planning calendar a lot sizing procedure PK to determine that MRP will generate planned orders in specific days of the week. However, this is a material master setting and it is not customer specific.

    As a workaround, you can try to define a different storage location MRP area for each customer and a different planning calendar for each MRP area.


    Regards,

    Caetano

    Add comment
    10|10000 characters needed characters exceeded