Skip to Content
0
Former Member
Dec 08, 2011 at 07:44 AM

PIR and Production Orders

145 Views

Hi all,

X product's strategy is 40 and it has 20 production orders, seen in MD04. In MD61 i have entered 40 PIR. In MD04 i want to see that 20 production orders and 40 planned orders after MRP run. But MRP run creates 20 planned orders. It creates PIR with VSF. I tried strategies 50 VSE and 10 LSF but it has no effects. How can i plan as told above?

Regards,

techmaster