Hi all,
X product's strategy is 40 and it has 20 production orders, seen in MD04. In MD61 i have entered 40 PIR. In MD04 i want to see that 20 production orders and 40 planned orders after MRP run. But MRP run creates 20 planned orders. It creates PIR with VSF. I tried strategies 50 VSE and 10 LSF but it has no effects. How can i plan as told above?
Regards,
techmaster
Dear Caetano,
Is there any way to plan PIR without considering existing production orders ?
Regards,
techmaster
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
There is no strategy with out considering Production orders.
strategy 11 will be used with out considering the stock.
refer below link
http://help.sap.com/saphelp_47x200/helpdata/en/cb/7f9b7043b711d189410000e829fbbd/frameset.htm
Regards,
srihari
Hi Techmaster
What you have described seems to be the standard behavior for strategy 40. MRP will create planned orders to cover the PIR quantity minus firmed receipt elements.
You would have to consider the existent production orders quantity when creating PIRs.
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
10 | |
6 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.