As per normal cycle if i create mentenance plan for equirment having 15 days cycle & schduling period is 365 days then after schduling i get 48 calls for 365 days it is as per staderd.
Now our requirment is every next call always trigger after complition of current call for taht confirmation require is ticked in plan.
but how can we do automatic reshduling of paln after UD done????
1.1.2011
15.1.2011
1.2.2011
15.2.2011
if my first call complited on 5.1.11 then next call i require after 15 days 20.1.2011 how can we do this automatically...