calibration cycle

Former Member
0 Kudos

Dear All.

As per normal cycle if i create mentenance plan for equirment having 15 days cycle & schduling period is 365 days then after schduling i get 48 calls for 365 days it is as per staderd.

Now our requirment is every next call always trigger after complition of current call for taht confirmation require is ticked in plan.

but how can we do automatic reshduling of paln after UD done????

1.1.2011

15.1.2011

1.2.2011

15.2.2011

if my first call complited on 5.1.11 then next call i require after 15 days 20.1.2011 how can we do this automatically...

Regards.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear,

You have maintain your requirement in T.Code IP11 like as per below,

Package No. Cycle length Unit Mai. Cycl. Text Cycle Text Hierarchy Hi. text Offset Offset text

1 Day 15 Days 1 1 01 15 1

2 Day 30 Days 2 1 01 30 2

3 Day 45 Days 3 1 01 45 3

Continue till your cycle end.

Regards,

Sandip

Former Member
0 Kudos

hi,

go for JoB scheduling, in Bkgrnd via IP10 / IP30.