Former Member
Dec 08, 2011 at 04:46 AM

Process Order operation scheduling duration calculation

879 Views

Hi

We have following formula has been maintained for processing time calculation in resource.

Machine * ( Operation quantity / Base quantity / Operation splits ) + Setup + Change-over

As per above formula for following procee order qty and time, SAP caulates time.

Opeartion qty - 100,

Base qty - 100,

Op split - 1

Machine - 0.5 hrs (30 Mins)

Processing time calculated as 30 mins (.5hrs)

When I schedule the process order with same resource for same qty and machine time, processing time is calculated as 33 mins. We dont have maintained any floats in scheduling margin key in material master. We dont have any wait times also.

Can you please let us know why process order operation is having 3 mins tolerance? Any idea where such settings has been maintained?

Any pointers will be helpful.