Dear PP Gurus,
Here is my case :
Stock Qty for Sparepart A : 100 un
First production will require 80 un A, and availability check confirmed. Second Production Order will require 70 un A, where 20 un confirmed and 50 un is not confirmed on availability check. When i try to goods issue the second production order, it is allowed to consumed all 70 un because unrestricted stock is 100. How can i forbid goods issue in second production order only for 20 un A which is confirmed before.
Thanks,
Arman Lie
Availability check is mainly for planning. I don't think you can restrict unrestricted stock, SAP assumes the stock can be used for anything not just as component to produce a material ( planned issue ). You may wanna try backflushing so that goods issue done in sync with confirmation of production orders, so that accidental issues are not done to production order scheduled later than others.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Arman,
If my understanding is correct then there is no control of issuing the goods to different orders (issuing to an order for which
originally there was a shortage or based on the orders created earlier in the system).
I guess there was a similar post here in PP forums itself,kindly use the serach option to get some more idea regarding the same.
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear
First of all what ever qty u release during production it well get copied in confirmation so as u said first production order is 80 so the balance qty is 20 out of 100 units so for 20 production order is confirmed so u need another production order for 70 in that case u have deflicit stock of 50 so for that reason ur production order not get confirmed for 50 in order to confirm this order u need t make a stock of 50.
1. check in the OPK4 enable the actual qty
2.check t-code OPJK Checking Rule and check when material availability when saving the order
and please check in the material master what availability check u have maintained in mrp
[http://help.sap.com/erp2005_ehp_04/helpdata/EN/cf/70124adf2d11d1b55e0000e82de178/frameset.htm]
With Regards
Pushpalas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.