Hi Gurus,

I am trying o set an MRP, type PD with EX lot size then i save an independent requirement at MD61, run the MRP at MD02 for the finished product but the values on the planned order don't make any sense.

Example:

Storage stock = 5000 Kg

Independent requirement = 100000 Kg

Planned order = 110604 Kg

Shouldn't the planned order be the requirement minus the existing stock (95000 Kg) ?

Thanks in advance for you help.

Kind Regards.